Make Each Project’s Evidence Visible

A milestone is a documented checkpoint, not a completion score. Unknown stages stay open until the records establish them.

El Portal Homes

Planned voucher expansion
  1. August 18, 2026

    Local Plan Action

    Adopted as amended; up to 120 project-based vouchers (PBVs) in the 2026 plan year.

  2. October 30, 2026

    Two-Phase Plan

    181 planned voucher units across two phases, not delivered homes.

  3. Not verified

    Final HUD Approval

    A forecast of approval is not the approval record.

  4. Not verified

    Signed Contracts

    Executed assistance contracts and effective dates still needed.

  5. Not verified

    New PBV Assistance

    Dated, aggregate households assisted under the expansion still needed.

Read El Portal’s Full Record and Sources

41

Households Reported Placed

Existing El Portal apartments, summer 2026. City report dated October 1, 2026.

A separate reported outcome. Do not treat these placements as delivery of the planned PBV expansion.

Read the City’s Placement Report

Craycroft + Lee Street

82 existing homes: 74 apartments + 8 duplex units. This is preservation, not 82 new homes or vacancies.

Financing plan submittedClosing not verified

The RAD tracker reviewed November 7, 2026 lists a submitted financing plan without a closing date. A blank field does not prove no closing occurred.

View the Preservation Record and Sources

Visual guide to existing published research. Source dates and limits are retained below. “Unknown” means not established in the reviewed records; a project’s status may have changed since its source date.

Documented Project Milestones

This is a curated selection from published research, not the full internal workbook. Each entry links to a previously published finding or evidence question and identifies what remains unverified.

Search scope: Search and topic filters apply only to the curated catalog entries below. They do not search the detailed project questions or outcome cohorts below, the full site or source documents. Read the detailed project questions.

Showing 5 research records.

Direct link

Amazon Flats

Place
Tucson
Stage & date
Announced groundbreaking · April 2026
Homes
59 apartments described
Funding record
Financial closing ratified April 8, 2026; actual disbursements remain unverified.

Separate from the 30-studio Amazon Motel conversion. Proposed vouchers and HOME designations are not additional homes.

Read the finding →
Dates, funding & sources

Announced groundbreaking · April 2026

59 apartments described

The County’s PO2500016491 packet uses the name “Amazon Flats” but describes $749,625 for conversion of a 30-room motel into 30 studios. That physical scope is the Amazon Motel conversion, separate from the 59-apartment Flats construction project. The April 8, 2026 EPHD legal action report records a 5–0 ratification of Amazon Flats’ financial closing.

Important limit: The action report does not supply the closing package or precise closing date, signed assistance contracts or actual Flats occupancy. The published County packet has blank signature and covenant lines; executed documents, completion reporting and certificates of occupancy remain record targets. Do not add 59 apartments, 39 proposed PBVs and two HOME-designated units as distinct homes.

Source: F-002 · SRC-113
Direct link

Craycroft Towers and Lee Street Duplexes

Place
Tucson
Stage & date
Existing housing · August 2026 notice
Homes
74 Craycroft + 8 Lee Street apartments
Funding record
82 project-based vouchers allocated; executed HAP contracts remain unverified.

These are existing homes, not 82 newly constructed apartments or available vacancies.

Read the finding →
Dates, funding & sources

Existing housing · August 2026 notice

74 + 8 existing apartments; 82 PBVs allocated

City notices describe 74 Craycroft and eight Lee Street apartments. The 82 Section 8 project-based vouchers concern the existing units, with RAD and Section 18 classifications also described for Craycroft.

Important limit: Not 82 newly constructed units or 82 available vacancies. Executed HAP contracts, occupancy and application procedures remain unverified.

Source: City notice cited in F-003
Direct link

Milagro on Oracle

Place
Tucson
Stage & date
Reported opened · January 2025
Homes
63 affordable apartments
Funding record
A comparable spending total is not established in this project summary.

A reported opening is not an audited resident count or a current vacancy listing.

Read the finding →
Dates, funding & sources

Reported opened · January 2025

63 affordable apartments

City announcements describe a housing-delivery milestone, crediting El Pueblo Housing Development and Gorman & Company and a combination of new construction and adaptive reuse.

Important limit: A reported opening is not an independently audited resident count or evidence of currently available apartments.

Source: City announcements cited in F-004
Direct link

Amazon Motel Conversion

Place
Tucson
Stage & date
Reported completed · September 2025
Homes
30 supportive-housing studios
Funding record
$749,625 described in County packet PO2500016491; execution remains unverified.

The packet uses the name Amazon Flats but describes the motel conversion. Published signature lines are blank.

Read the finding →
Dates, funding & sources

Reported completed · September 2025

30 supportive-housing studios

The City reports the 30-studio motel conversion completed in September 2025. County contract PO2500016491 uses the name “Amazon Flats” but describes $749,625 for the 30-room motel-to-studio conversion, separate from the 59-apartment construction project.

Important limit: Published signature and covenant lines are blank. Executed documents, completion evidence, current vacancies and retention remain unverified.

Source: F-011 · SRC-112
Direct link

Tucson House Renovation

Place
Tucson · 15th floor
Stage & date
Renovation milestone announced · October 16, 2026
Homes
24 renovated apartments announced
Funding record
A comparable project-spending total is not established in this summary.

The 24 apartments and 25 announced households remain unreconciled. The permit register lists a November 15, 2026 expiration. The issue date, current permit validity and vacancies remain unverified.

Read the finding →
Dates, funding & sources

Reported milestone · October 16, 2026

24 renovated apartments on the 15th floor

The City permit page shows an October 15, 2026 application for TC-CFO-1026-00207. The register listed the permit as Issued when reviewed November 7 for temporary occupancy associated with Tucson House’s 15th-floor Level 4 renovation. The issue date remains unverified. The register lists a November 15, 2026 expiration. The October 20 PHA report says the renovation was 30% complete, the 15th floor was finished and residents were moving back.

Important limit: The October 16 announcement’s 24 apartments and 25 households remain unreconciled. Neither the permit register nor the later narrative verifies a completed move count, new admissions or current vacancies. The original certificate and any conditions or renewal still need verification.

Source: F-012 · SRC-106 · SRC-109 · SRC-110

Project Plans, Assistance and Remaining Questions

Selected questions updated November 7, 2026. Latest evidence review; earlier source dates and remaining limits are retained.

Resident privacy: Questions about assistance and outcomes seek aggregate counts, not residents’ identities or individual records. See our privacy standard.

Posted: . Source dates are identified below.

When housing funding is announced, what happens next? Each answer separates what the records show from what still needs checking. “Unknown” means not established by the records reviewed here. A project’s status may have changed since its source date.

Q-015 · added November 6, 2026

What Is Planned for Craycroft and Lee Street?

Documented: The plan is to rehabilitate 82 existing homes: 74 apartments and eight duplex units. El Pueblo Housing Development (EPHD) also describes a Rental Assistance Demonstration conversion, which changes their subsidy structure.

Federal records show an environmental milestone and a submitted financing plan for the 82-unit preservation project. The RAD tracker reviewed November 7 lists “Financing Plan Submitted” without a closing date. Closing, proceeds and signed assistance contracts remain unverified.

Unknown: Which budget and bedroom count govern? The November presentation lists 124 bedrooms in its summary and 85 in its detailed slide. The summary cost entry is $33.9, without a millions label; the detail gives $34.7 million.

Next: Confirm the governing budget and bedroom count, then document public contract status, aggregate occupancy totals and published application and referral rules.

Source date: EPHD project page update August 6, 2026; presentation November 5, 2026, PDF pp. 12 and 31. [5, 6]

Updated . SRC-098 · SRC-099 · SRC-100 · November 7 review

Citation correction: the previous link opened a different project’s review. The correct HUD document records 7015.16 certification on September 1, 2026. Read the citation correction and source limits.

Q-016 · added November 6, 2026

What Assistance Is Authorized for El Portal Homes?

Documented: The August 18 PHA packet supports the up-to-120 El Portal voucher plan; its attached amendment is a public-comment draft, and the local action was adopted as amended. The October 30 memo estimates 181 planned voucher units across two phases, not delivered new homes. Separately, the City’s October 1 newsletter reports 41 households placed in existing El Portal apartments over the summer with Housing First assistance. That report does not establish implementation of the planned voucher expansion.

The memo forecasts about $1.15 million in additional annual rental revenue across both phases, subject to rent reasonableness. A second phase is anticipated in a subsequent plan year, subject to vouchers, program limits and required plan approvals.

Unknown: Final HUD approval, signed assistance contracts and dated totals of households receiving the new PBV assistance remain unverified. The October 20 PHA report anticipated related HUD approvals during October–December; that expectation is not approval. Final effective operating policies, completed inspections and rent determinations remain to be verified.

Next: Obtain aggregate counts of contracted units and households assisted, with reporting dates, inspection-completion totals and effective program policies. Do not request resident names, unit-level addresses or individual case records.

Source date: City memo October 30, 2026, pp. 1–2; it reports the August 18 plan approval. [7]

Updated . SRC-101 · SRC-105 · SRC-106 · November 7 review

Program Outcome Cohorts

These dated program outcomes describe specified groups of people and reporting periods, not physical project milestones. Each record retains its own denominator, exclusions and limits. Follow-up seeks aggregate counts, not individual resident records.

Show the People Behind the Percentage

Housing First: keep the denominator, exclusions and reporting dates in view. These are different cohorts, not a single funnel.

Exits to Permanent Housing

21 / 36

58.3%

Of the leavers included in this measure

July 1, 2025–June 1, 2026

Each tile represents one recorded leaver. The counts are given in text below.

  • 21 permanent-housing exits (solid teal)
  • 15 other included exits (pale fill)
  • 8 excluded from the calculation (hatched)
  • 44 leavers before exclusions

Not everyone served. Not a Countywide rate. Score points are not success percentages.

Source: TPCH Scorecard and Definitions

A Different, Earlier Cohort

7 / 43

16.3%

Recorded returns to homelessness within 12 months after a permanent-housing exit.

Earlier exit cohort: June 1, 2024–June 1, 2025. Do not subtract this from the exit rate.

What “Exit” and “Return” Mean

“Exit” means leaving the assistance program with permanent housing recorded as the destination. The later recorded return does not establish its cause or whether someone chose to leave housing.

Source: TPCH Methodology, p. 26

26 / 26

Recorded Openings Filled Through Coordinated Entry

July 1, 2025–June 1, 2026. This describes the referral route into those openings, not access for everyone waiting.

Source: TPCH FY2026 scorecard, final July 13, 2026, and FY2026 methodology, pp. 24–26. The specific destinations of the eight excluded leavers are not established here. Read the full outcome record and privacy limits.

What Do County One Stop’s Results Tell Us?

The TPCH FY2026 scorecard reports 17 of 24 County One Stop rapid-rehousing leavers exiting to permanent housing (70.8%) for July 1, 2025–June 1, 2026, with no excluded leavers. A separate earlier group had 13 of 24 people return to homelessness within 12 months (54.2%); that cohort exited to permanent housing during June 1, 2024–June 1, 2025.

These are people in one project and two different cohorts, not a Countywide success rate or one group’s retention result. Matched reporting periods, inclusion rules and aggregate follow-up outcomes are needed before comparing costs or broader program performance.

Original Scorecard · Full November 7 Review

Q-017 · added November 6, 2026

What Do Housing First’s Results Tell Us?

Documented: The FY2026 scorecard reports:

  • Did people leave for permanent housing? Yes, 21 of 36 leavers included in the calculation, or 58.3%, did. The period is July 1, 2025–June 1, 2026. The scorecard starts with 44 leavers and excludes eight based on their destinations. It does not measure everyone served.
  • How were openings filled? All 26 recorded openings were filled through Coordinated Entry in the same period. That describes the referral route into those openings, not access for everyone waiting.
  • Did people return to homelessness? Seven of 43 people who exited to permanent housing in the earlier June 1, 2024–June 1, 2025 period returned within 12 months, or 16.3%. This is a different group and reporting period.

Housing First’s 50/100 and MDOT’s 10/40 are weighted scores, not housing-success percentages. Both programs were exempt from the grant-expenditure measure. Their scores do not establish underspending.

Unknown: The aggregate destination categories accounting for the eight excluded exits are not established. Later aggregate outcomes and costs for comparable groups and reporting periods also remain unverified.

Next: Obtain an agency-prepared aggregate breakdown by broad destination category and updated outcome totals, with inclusion rules, denominators and reporting periods. Combine or suppress small groups where individuals could be identified; do not request participant records.

Source date: TPCH scorecard July 13, 2026; FY2026 methodology pp. 24–26. Exact cells and definitions appear in source 8 and source 9.

Posted: . Source dates and cohort periods are identified in this record.

Research Standards

Plans, awards, commitments, expenditures, restricted balances, completed housing, and actual vacancies are separate measures. Published figures have limited reporting periods and may rely on historical agency statements. Questions are not findings of fraud or noncompliance.

Detailed source records remain in the Public Evidence Index. Corrections and additional official records can be shared through Contact.